Link Project Schedule without PMWeb Scheduling Module
You can link your Primavera or MS Project Schedule to link to other PMWeb Modules without licensing the PMWeb Scheduling Module.
Navigation Path: Portfolio>Projects
 Link Schedule
Press to open the "Link Schedule" dialogue box
|
 Schedule Type
Select the type of schedule to be linked
|
 Browse
Browse out to find the XML file to be linked
|
 Upload
Click to upload the XML schedule file and show the list of schedule items
|
 Import WBS codes
Select to import the items listed in the WBS Code column
|
 Update Previously Linked Tasks
Select to update previously linked schedule tasks. If not checked, new line items will be created.
|
 Save and Exit
Click to complete the upload and close the "Link Schedule" dialogue box
|