A Progress Invoice (also referred to as progress billing, percentage of completion billing, or partial billing) is used to track an invoice from a vendor or subcontractor against a Commitment.
Navigation Path: Cost Management > Invoices > Progress Invoices
Select Requisition
Use to search for existing Progress Invoices.
|
Add
Click to add new Progress Invoice.
|
Header Details
Project: Used to select the project associated with the Requisition.
Commitment: Select the Commitment the invoice is associated with.
Company: The Company will be automatically populated (once the record is saved) based on the Commitment that you selected.
Description: Enter a Description for the Progress Invoice (ie. January Invoice, etc.)
Reference: Enter any required reference information.
Invoice #: This field will automatically be populated by PMWeb with the next consecutive invoice number for the selected Commitment.
Record #: This field will automatically be populated by PMWeb.
Revision: Enter the revision number.
Date: This field will automatically be populated by PMWeb with the current date.
Status: The status (draft, submitted etc.) will automatically be updated by PMWeb based on the workflow configuration.
Cost Period: Select the cost period associated with the Commitment. This field is configured by your Administrator in the Portfolio>Lists>Periods menu.
Category: Select a Category for this invoice. This field is configured by your Administrator in the Portfolio>Lists>Lists menu.
|
Save
Click to save the header details of the form.
|
Contract Snapshot
These fields provide an overview of the contract. This area will be populated after you save the header details and add line items to the contract.
|
On Line Invoice
This area can be used by vendors/contractors to submit their invoices in PMWeb.
Invoice Date: Enter the date of the invoice.
Invoice Due: Enter the date that that invoice payment is due.
Invoice Type: Select whether this is a progress invoice or the final invoice to close out the commitment.
Contact: Enter the name of the the person to contract regarding this invoice.
Comment: Enter any general comments regarding the invoice.
Print Lien Waiver: The Print Lien Waiver button prints a standard lien waver form.
Signed Lien Waiver Attached: Check this box to note that there is a lien waiver attached.
|
Adjustments
Click to enter adjustments (fees, insurance, taxes etc.) to the Progress Invoice. See the Commitments>Adjustment section of the guide for more details
|
Use Units
This field will allow you to enter units of measure and quantities of that item. If this option is not selected, the line item will be a lump sum value.
|
Change Orders
Click to add EXISTING approved change orders so you can invoice against them. A screen will appear with a list of change orders. Select the change order(s) you want to add by placing a check mark to the left of the change order name. Once all items are selected click save.
Note: The change order date must be today or prior to the current date. PMWeb will not allow you to invoice against something that is in the future.
|
Line
This field will be automatically populated by PMWeb based on the commitment selected.
|
Description
This field will be automatically populated by PMWeb based on the commitment selected.
|
Cost Code
This field will be automatically populated by PMWeb based on the commitment selected.
|
Scheduled Value
This field will be automatically populated by PMWeb based on the commitment selected.
|
Stored Material
Enter the value of the equipment.
|
Prior Invoices
This field will be automatically populated by PMWeb based on the commitment selected.
|
Total This Invoice
This field will automatically be populated by PMWeb based on the values in the % complete, scheduled value and current invoice fields.
|
Total Invoice
This field will automatically be populated by PMWeb based on the values in the % complete, scheduled value, current invoice fields prior and current invoice fields.
|
Current Invoice
Enter the total amount to be paid for the line item.
|
% Complete
Enter the percentage complete for the line item. This value will also be calculated based on the values in the scheduled value, prior invoices, stored materials and current invoice fields.
|
Balance to Invoice
This field will automatically be populated by PMWeb based on the values in the % complete, scheduled value prior and current invoice fields.
|
Services Retain %
Enter the retainage percentage amount for the line item. When you are ready to release the retention, edit the line and enter 0 dollars in the retain % or retain amount column.
|
Service Retain Amount
Enter the retainage for services for the line item.
|
Material Retained %
Enter the percentage of retainage for the material/equipment.
|
Materials Retain Amount
Enter the material/equipment retainage amount.
|
Total Retained
This field will be automatically populated by PMWeb based on the values in the services retain amount and materials retain amount fields.
|
Phase
Select the phase (construction, design etc). This field is configured by your Administrator in the Portfolio>Lists>Projects menu.
|
CCO#
This field will be automatically populated by PMWeb with the Commitment Change Order number associated with the line item.
|
Location
Select the location where the work was performed. This field is configured by your Administrator in the Portfolio>Lists>Projects menu.
|
Cost Type
Select the cost type (equip., labor etc.) associated with the line item.
|
Notes
Enter additional details regarding the line item.
|
Req. Code
This field will be automatically populated by PMWeb based on the Req. Code entered on the selected Commitment.
|
Task
Select the task associated with the line item. The options are configured within the schedule module.
|
Assigned To
Select the company the item is assigned to.
|
Orig./Rev.
This field will be automatically populated by PMWeb based on the whether the line item is part of the Original Commitment or as the result of a revision.
|
Create Next
Click to create the next Progress Invoice. The information from this invoice will be copied to the new invoice. Note: The "Create Next" button will only be available on the LAST invoice for each commitment once it's in a status of Approved.
|
|