Link Project Schedule without PMWeb Scheduling Module
You can now link your Primavera or MS Project Schedule to link to other PMWeb Modules without licensing the PMWeb Scheduling Module.
Navigation Path: Portfolio>Projects
Link Schedule
Press to open the "Link Schedule" dialogue box
|
|
Schedule Type
Select the type of schedule to be linked
|
|
Browse
Browse out to find the XML file to be linked
|
|
Upload
Press to upload the XML schedule file and show the list of schedule items
|
|
Update Previously Linked Tasks
Select to update previously linked schedule tasks. If not checked, new line items will be created.
|
|
Allow WBS codes to be imported
Select to import the items listed in the WBS Code column
|
|
Save and Close
Press to complete the upload and close the "Link Schedule" dialogue box
|
|